How we structure a website project: from brief to launch

The phases a website project goes through with us, what each produces, what we need from the client at each, and how long each usually takes.

5 minread 1,072words last updated

The short answer

A website project with us runs through six phases, and each one ends with something the client can see and approve before the next begins. Six to twelve weeks is typical for a full project; a defined package is shorter. The brief and audit establish what the site must do, for whom, and what the current site and accounts look like. Content and structure define what the site says and how it is organised, and start in week one because content decides the schedule. The design system turns the brand into tokens and components the whole site will be built from. The build assembles pages from those components, with a preview link for every change. Testing and content loading bring the site to launch quality: accessibility, performance, security, forms, redirects, real content in every page. Launch is a checklist followed in a quiet window, and the first month afterwards is part of the project, watching real visitors and finishing what they reveal. Six to twelve weeks is typical for a full project; a defined package is shorter, and the variable is almost always content.

The six phases

PhaseWhat happensWhat it producesWhat we need from youTypical duration
1. Brief and auditGoals, audiences, offerings, constraints; audit of the current site, accounts, analytics and rankingsOne-page brief; audit report; project planHonest answers; access to accountsOne to two weeks
2. Content and structureSite map; page types; content model; content plan; writing or gathering beginsSite map; content model; content scheduleDecisions on offerings and structure; content owner namedStarts week one; runs in parallel
3. Design systemTokens, typography, components, key page designsDesign system; approved key pagesFeedback on design within daysTwo to three weeks
4. BuildPages assembled from components; forms, integrations, redirects; preview for every changeWorking site on previewsFeedback on previewsTwo to four weeks
5. Testing and content loadingAccessibility, performance, security, forms, redirects; all real content in place; launch checklist; the site goes to a private staging address for your acceptance reviewLaunch-ready site; checklist complete; written acceptanceYour review inside the acceptance windowOne to two weeks
6. LaunchDNS switch in a quiet window; monitoring on; the redirect map completed from the not-found logLive site; launch reportAvailability at launchLaunch day

The acceptance window, and it is the one deadline that can cost you something

Phase five ends with the site delivered to a staging environment for you to review. In our terms that review window is 10 to 15 business days, and work you do not reject in writing inside it counts as approved; revision rounds beyond the ones in your package are billed at the add-on rate. Phase approvals happen in meetings, but this one runs on a clock whether or not anybody meets.

It is the only deadline in our contract where doing nothing costs you a right, which is why it is on this page rather than only in the small print. Put it in your own calendar next to ours, and ask any supplier the same two questions before you sign: how long is the acceptance period, and what happens if we let it pass?

How the phases connect

  1. The brief decides the structure; nothing is designed until the site’s purpose is written down.
  2. The structure decides the content model and the page types the design system must cover.
  3. The design system is built before pages, so pages are assembled rather than designed one by one.
  4. The build runs on previews from the first day, so the client watches the site appear.
  5. Content lands as it is ready, into the structured model, and the schedule tracks it.
  6. Testing runs in the pipeline throughout and is confirmed in full before launch.
  7. Launch follows the checklist, and the first month closes the loop with real data.

What the client sees along the way

The brief and audit as documents. The site map and content model as a plan they can react to. The design system and key pages as approved designs. The build as preview links that change daily. The testing as reports. The launch as a checklist with ticks. The first month as a report with real numbers. At no point is there a reveal; there is a steady view of the site becoming itself.

What this means for you

A website project with a clear structure runs through brief, content and structure, design system, build, testing and launch, with something to approve at the end of each and a first month that finishes the job. Your part is decisions, content and feedback on a schedule. Content sets the pace, so it starts first. Done this way, the launch is a checklist rather than a leap, and the site that goes live is the one you watched being built.

Written by the CivSec S.M.A.R.T team

We build and run websites, software and AI systems for businesses. We write about what we see in that work, in plain language, and we update articles when things change.

Last checked . Spotted something outdated? Tell us.

Frequently asked questions

How long does a business website take?

A full project with all six phases runs six to twelve weeks from brief to launch; a defined package is shorter, and the package pages say how much. Content readiness is the largest variable. The design system and build phases are predictable; the content phase depends on how quickly the client can decide, write and approve. Projects that run long almost always run long there, which is why we start content work in the first week.

What do you need from us?

A named decision-maker, honest answers in the brief, content or the time to produce it with us, access to accounts in your name, feedback on previews within a few days, and attendance at the phase approvals. The list is short, and each item is on the schedule so nobody is surprised when it is due.

What happens after launch?

The first month is when a launch is judged, so agree in advance who does it and whether it is included. What belongs in it: monitoring and analytics watched, what real visitors reveal fixed, the redirect map completed from the not-found log, and a review at the end of the month. After that the site moves into the monthly partnership if there is one, or is handed over with documentation and access if there is not.